This service allows for the re-registration of the project under the same developer or a new one, either through a decision by the Judicial Committee for Cancelled Projects or upon the developer’s request, after fulfilling all registration requirements and obtaining all necessary approvals and permits from the relevant licensing authorities
1- An undertaking form to assume obligations
2- notice form
1. Judicial Committee decision for acquisition or developer’s request.
2. Fill the declaration form and publish the re-registration announcement in approved newspapers within 3 days.
1- Fulfill all requirements or conditions set by the Judicial Committee.
2- Complete the land transfer procedures with the Real Estate Registration Services Department.
AED 150,000
AED 10 knowledge fee
AED 10 innovation fee
Step 1: Submit the request via the system based on the Committee's decision or upon the developer's request.
Step 2: Fill out and upload the undertaking and announcement forms after 15 days from the date of the last announcement.
Step 3: Open a unit survey request if there is a modification in unit data or a need to re-link units.
Step 4: The developer submits a request to the Account Custodian to open the account and fill in the account data.
Step 5: Receive, audit, and review the new project registration request, then accept or reject it.
Step 6: Pay the registration fee.
Step 7: Receive the certificate through the electronic system.
Noqodi Wallet
Land Department website (Real Estate Developers Portal - Contracts) Trust Account System
Real estate project approval certificate (e-certificate )
3 Working days
DET
DM
DEWA
Civil Defense
Banks
Main Developers
Company